BP and Iberdrola Fire Up Spain's Largest Green Hydrogen Plant — 20% Paid by EU
BP's 25 MW Castellón electrolyser is running, producing 2,800 tonnes of green hydrogen a year. Total cost: €70m, of which €15m came from EU funds.

BP and Iberdrola started operations at a 25 MW electrolyser next to BP's Castellón refinery — Spain's largest green hydrogen plant, capable of producing around 2,800 tonnes a year to displace grey hydrogen at the site. For investors, the question is less whether the plant works than whether it earns its cost of capital without public money.
What happened
The plant is run by Castellón Green Hydrogen SL, a 50/50 joint venture, and uses a Plug Power PEM electrolyser. It was originally due to start in May, and was once conceived at 200 MW — a reminder of how far European hydrogen ambitions have been scaled back.
The numbers tell the story. Total cost was €70m, of which €15m — just over 20% — came from NextGeneration EU funding.
Markets had no obvious reaction: with AI and chip volatility and rate questions dominating the week, a 25 MW start-up is a rounding error for a company of BP's size. See how stock prices are made for why single project news rarely moves a mega-cap.
Why it matters
This is the most defensible kind of green hydrogen project: on-site, replacing grey hydrogen the refinery already buys, behind existing infrastructure and paid for partly by grants. Compare Repsol's €400m final investment decision on a 150 MW plant in Tarragona — similar logic, much larger cheque.
The catch is that even the good projects only happen with subsidy support. Phase 2 of the Castellón venture has already secured €66.3m in regional government funding — more than the entire first phase cost — and Spain redirected €211m of IPCEI funds toward the expansion in June. Earlier, bp, Iberdrola and EDP were dropped from a €1.2bn Hydrogen Valley programme.
So investors should treat this as an engineering success and a policy read-out, not a step change in economics. Hydrogen's problem in Europe has never been a shortage of megawatts on slides; it is delivered cost and the fact that the subsidy decides the return. BP's equity story still rests on buybacks, debt and a disciplined transition budget — and a €70m JV stake does not change it either way. See reading the balance sheet to weigh capex against cash returns.
What to watch next
- BP's fourth-quarter results and 2027 capital allocation update — whether low-carbon spending holds or shrinks again
- Any final investment decision on Castellón Phase 2 and the size of further grant awards
- Spanish and EU state-aid decisions: how much of Repsol's Tarragona spend is covered
- Electrolyser economics: utilisation and power prices behind the 2,800-tonne run rate
- Wider utility capex plans into the 2027 reporting season